Multi-Project Concurrent Integration
Cobra leverages the PM Compass Process Server to implement the multi-project concurrent integration feature.
You can load a single import file with data from multiple projects concurrently instead of sequentially when using
. This means if there are 10 projects in the import file, Cobra will load these projects all at the same time.Cobra creates a single-project integration for each project and submits that integration job to PM Compass Process Server. PM Compass then distributes each integration job to a Cobra Web Service.
Cobra submits a single job (.csv file) containing multiple projects. When it gets submitted to the Cobra Process Server, the server breaks that job up into a bunch of smaller individual jobs, one for each project. The Cobra Web Service Gateway Service distributes each integration job to one or more Cobra Web Services.
Before You Begin
- You must fully understand the requirements and the steps in setting up your environment to run a concurrent process. Refer to Deltek PM Compass and Cobra Concurrency Solution Setup and Configuration Guide.
- You are integrating an import file with data from multiple projects.
- Related Topics:
- Load an Import File with Multiple Projects Concurrently
Run the Integration Wizard to load an import file with multiple projects concurrently. - Integration Errors
If the integration process completes with errors, you need to correct the errors and perform the integration again. - View Job Status and Process Logs
You can view the job status and process logs both in Cobra and PM Compass.